      2007 Current Projects

       

       

      Interstate-85 Corridor - System Pressure Improvement

      35,312 feet of new 6 inch, high pressure, steel line was placed in operation on June 2007 to provide improved gas service to the Interstate-85 corridor.

       

      Steve Reynolds Industrial Blvd - Industrial Park Project Main

      7,700 feet of new 4 inch, high pressure, steel and 7900 feet of 4 inch plastic gas main for the new John Rooker developed industrial park.

       

      Chapman Development - Homer Road Commercial/ Residential Development

      7,925 feet of new 4 inch plastic approach main was installed in May 2007.  As the project progresses, 1200 feet of 4 inch plastic and 2700 feet of 2 inch plastic main  will be needed.